EstatePass
Contract AdminContractsmedium40% of exam part

A time and materials contract specifies labor at $85/hour and materials at cost plus 15%. If 40 hours of labor and $8,000 in materials are used, what is the total billing?

Correct Answer

A) $13,200

Labor cost: 40 hours × $85/hour = $3,400. Material cost: $8,000 × 1.15 = $9,200. Total billing: $3,400 + $9,200 = $12,600. Wait, let me recalculate: $8,000 + ($8,000 × 0.15) = $8,000 + $1,200 = $9,200. Total: $3,400 + $9,200 = $12,600. The answer should be $12,600, but that's option B. Let me check again: $9,200 + $3,400 = $12,600. Actually, $8,000 × 1.15 = $9,200, and $9,200 + $3,400 = $12,600. There seems to be an error in my calculation setup.

Answer Options
A
$13,200
B
$12,600
C
$14,200
D
$12,400

Why This Is the Correct Answer

The correct answer is actually B) $12,600, not C) $13,200 as stated. The calculation shows labor cost of $3,400 (40 hours × $85/hour) plus material cost of $9,200 ($8,000 × 1.15 for the 15% markup) equals $12,600 total. The explanation provided correctly calculates to $12,600 but incorrectly identifies this as option C when it's actually option B.

Why the Other Options Are Wrong

Option C: $14,200

$14,200 is significantly higher than the correct answer and likely results from a major calculation error, possibly double-counting markup or using an incorrect hourly rate

Option D: $12,400

$12,400 is incorrect because it likely represents an error in calculating the material markup, possibly using only a 10% markup ($8,000 × 1.10 = $8,800) plus labor ($3,400) which would give $12,200, or some other calculation error

Memory Technique

Remember 'T&M = Time + Materials': Time (hours × rate) + Materials (cost × markup multiplier). For percentages, convert to multiplier (15% markup = 1.15 multiplier).

Reference Hint

Florida Building Construction Standards - Chapter on Contract Types and Pricing Methods, or Construction Contracting Business and Law section covering Time and Materials contracts

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.