A safety meeting reveals that 3 workers out of 50 on site have not completed required fall protection training. What immediate action should be taken?

Correct Answer

A) Remove them from work involving fall hazards until training is complete

Workers without required fall protection training must be removed from work involving fall hazards until proper training is completed. This protects worker safety and maintains OSHA compliance.

Answer Options
A
Remove them from work involving fall hazards until training is complete
B
Have them sign additional safety waivers
C
Give them a brief on-site training session
D
Allow them to work under close supervision

Why This Is the Correct Answer

OSHA regulations require that workers receive proper fall protection training before being exposed to fall hazards. Removing untrained workers from fall hazard areas is the only legally compliant and safe option. This immediate action prevents potential injuries, fatalities, and OSHA violations that could result in significant fines and work stoppages. The workers can return to fall hazard work areas only after completing the required training and demonstrating competency.

Why the Other Options Are Wrong

Option B: Have them sign additional safety waivers

Safety waivers cannot waive OSHA training requirements or absolve the employer of responsibility for worker safety. OSHA regulations are mandatory and cannot be waived by employee agreements.

Option C: Give them a brief on-site training session

Close supervision cannot substitute for required fall protection training. OSHA standards mandate specific training requirements that must be completed before workers can be exposed to fall hazards, regardless of supervision level.

Memory Technique

Think 'STOP before you DROP' - untrained workers must STOP working in fall hazard areas before someone gets hurt from a DROP/fall

Reference Hint

OSHA Construction Standards 29 CFR 1926 Subpart M - Fall Protection, specifically 1926.95 and 1926.503 regarding training requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.