A project has liquidated damages of $1,500 per day and is completed 12 days late. The contractor incurred $8,000 in additional costs to accelerate the work. What is the contractor's total delay-related cost?

Correct Answer

D) $26,000

Total cost includes both the liquidated damages ($1,500 × 12 days = $18,000) and the acceleration costs ($8,000), totaling $26,000.

Answer Options
A
$8,000
B
$18,000
C
$10,500
D
$26,000

Why This Is the Correct Answer

The contractor's total delay-related cost includes both the liquidated damages penalty and the additional costs incurred to accelerate the work. Liquidated damages are calculated as $1,500 per day × 12 days = $18,000. The acceleration costs of $8,000 are added to this amount. Therefore, the total delay-related cost is $18,000 + $8,000 = $26,000.

Why the Other Options Are Wrong

Option B: $18,000

This only accounts for the acceleration costs ($8,000) but ignores the liquidated damages penalty of $18,000 that the contractor must pay for being 12 days late.

Option C: $10,500

This appears to be an arbitrary calculation that doesn't properly account for either the full liquidated damages amount or the acceleration costs.

Memory Technique

Remember 'TOTAL = LD + AC' (Liquidated Damages + Acceleration Costs) - both penalties hit the contractor's bottom line

Reference Hint

Look up contract administration and liquidated damages clauses in construction law references or project management chapters

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.