EstatePass
Contract AdminContractsmedium40% of exam part

A contractor submits Application for Payment #8 requesting $125,000. The contract allows 5% retainage, and $15,000 was previously retained. If this payment request is approved, what amount should the contractor receive?

Correct Answer

B) $118,750

The contractor receives the payment request minus retainage: $125,000 - (5% × $125,000) = $125,000 - $6,250 = $118,750. Previously retained amounts don't affect the current payment calculation.

Answer Options
A
$103,750
B
$118,750
C
$115,000
D
$110,000

Why This Is the Correct Answer

The correct answer is A) $118,750 because each payment application is calculated independently. The contractor receives the full payment request amount minus the current retainage percentage applied to that specific payment. The calculation is straightforward: $125,000 - (5% × $125,000) = $125,000 - $6,250 = $118,750. Previously retained amounts are tracked separately and don't reduce the current payment.

Why the Other Options Are Wrong

Option A: $103,750

This incorrectly subtracts both the current retainage ($6,250) and the previously retained amount ($15,000), double-penalizing the contractor by applying past retainage to the current payment.

Option C: $115,000

This incorrectly subtracts a flat $10,000 from the payment request, which doesn't correspond to the 5% retainage calculation and appears to be an arbitrary deduction.

Memory Technique

Think 'Each App Stands Alone' - each Application for Payment is calculated independently, with retainage applied only to that specific payment request amount.

Reference Hint

AIA Document A201 - General Conditions, Section 9.3 Applications for Payment, and Florida Statutes Chapter 713 regarding construction payments and retainage

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.