EstatePass
Contract AdminPermitsmedium20% of exam part

A construction project will impact 0.75 acres of wetlands. The mitigation requirement is 2:1 replacement ratio. How many acres of wetland mitigation must be provided?

Correct Answer

C) 1.5 acres

With a 2:1 mitigation ratio, the required mitigation is: 0.75 acres impacted × 2 = 1.5 acres of wetland mitigation. This ensures no net loss of wetland functions and values.

Answer Options
A
2.0 acres
B
1.0 acres
C
1.5 acres
D
1.25 acres

Why This Is the Correct Answer

Option C is correct because wetland mitigation follows a simple multiplication formula. When the impact is 0.75 acres and the required mitigation ratio is 2:1, you multiply the impacted area by the ratio factor. This calculation yields 0.75 × 2 = 1.5 acres of required mitigation. The 2:1 ratio ensures that for every acre of wetland lost, two acres are restored or created to maintain ecological balance.

Why the Other Options Are Wrong

Option B: 1.0 acres

Option B (1.25 acres) represents an incorrect 1.67:1 ratio, which falls short of the required 2:1 mitigation standard and would not meet regulatory compliance requirements.

Option D: 1.25 acres

Option D (2.0 acres) would represent a 2.67:1 ratio, which exceeds the required mitigation and would result in unnecessary additional costs and land use for the project.

Memory Technique

Remember 'IMPACT × RATIO = MITIGATION' - think of it as 'paying double' for environmental damage. The ratio tells you how many times larger your mitigation must be than your impact.

Reference Hint

Florida Building Code Chapter 1, Environmental Regulations section, or DEP Chapter 62-330 F.A.C. regarding wetland mitigation requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.